WS 3 — Implementation Roadmap & Cost Estimate
| Duration | 2 weeks |
| Objective | Translate the target state architecture into an implementation roadmap identifying the sequencing, dependencies and milestones required to move from the current environment to the target state |
| Deliverables | D3.1 · D3.2 · D3.3 |
Tasks
| ID | Activity (SOW Schedule "A") | Output | Status |
|---|---|---|---|
| WS3-A1 | Define major implementation work streams and capabilities required to realize the target state | Work stream definitions | ⚪ |
| WS3-A2 | Develop sequencing logic — business priorities, technical dependencies, organizational readiness, incremental value | Sequencing rationale | ⚪ |
| WS3-A3 | Identify key dependencies across platforms, applications, integrations, data, identity, infrastructure and participating lines of business | Dependency map + diagram | ⚪ |
| WS3-A4 | Identify critical path activities and key milestones | Critical path | ⚪ |
| WS3-A5 | Define the phased implementation roadmap — initiatives, sequencing, dependencies, indicative timing | Roadmap + diagram | ⚪ |
| WS3-A6 | Develop transition considerations for current to target state | Transition plan | ⚪ |
| WS3-A7 | Identify key risks and constraints of the transition, with mitigation strategies | Risk register | ⚪ |
| WS3-A8 | Create two implementation cost options — Konrad-owned delivery; co-delivery | D3.2 | ⚪ |
| WS3-A9 | Develop ROM implementation estimates for each option | ROM estimates + basis of estimate | ⚪ |
| WS3-A10 | Prepare the executive summary of roadmap, options and recommended path forward | D3.3 | ⚪ |
| WS3-A11 | Conduct the executive readout | Readout · next steps · engagement close | ⚪ |
Working notes
Three candidate spines, already written by the client
A2 does not start from nothing. Three artifacts in the client material already contain sequencing logic, and the roadmap will most likely be a reconciliation of them rather than a fourth invention:
- The strategy's seven workstreams across three phases, each with an owner and a layer, explicitly designed so none waits on the others.
- The assessment's nine conditions, already ordered by severity with 1–3 marked prerequisite to any further review.
- The experience map's build classification, separating promote-to-production from net-new build from procurement, zone by zone.
Reconciling three client-authored sequences into one is a much stronger position than presenting our own — it makes the roadmap theirs, and it makes disagreements visible instead of implicit.
Dependencies already visible
For A3, before any new analysis:
| Dependency | Gates |
|---|---|
| SIT / UAT / PROD / DR Redis provisioning | Integration test, performance test, penetration test, DR drill |
| A non-production environment that exists | The mandatory authenticated penetration test |
| Volumetry and the FCC capacity answer | API strategy, cache design, NFR catalogue, performance test, and the cost estimate |
| NFR catalogue and signed SLOs | Anything that has to be tested against a number |
| Privacy Office position | Customer-facing release |
| Named accountable owner for the shared runtime | Incident response, cross-BU decisions, and the co-delivery cost option |
| CAUCE / CAUEX reconciliation | Evidencing what is actually built |
| Re-homing Readiness, Testing, GTM, Stabilization, Scale Planning | Launch readiness — currently owned by nobody |
Risks to carry into A7
- Environment slippage — recorded in the client's own review as the programme's number-one schedule risk.
- The cancelled operational workstreams — cancelled in the CAUCE-to-CAUEX replan with no inheritor. A roadmap that does not re-home them repeats the mistake.
- Operating model as a gating dependency we cannot resolve — SOW §3.0 puts operating model design out of scope. We sequence around it and name it; we do not build it.
- Criticality tier unresolved — Gold versus Critical Digital Properties changes every recovery commitment by roughly an order of magnitude, and therefore the DR work in the roadmap.
- Cutover with no bypass — the dashboard replaces the only post-login route to every BU portal.
On the cost options
The co-delivery option's viability depends on Manulife staffing that the client's own material describes as absent — "no shared platform team funded to run them", and four components with no business-unit home. Price it, present it fairly, and name that dependency explicitly. A co-delivery number that quietly assumes a team which does not exist is not a cost option, it is a forecast of a slip.
Engagement close
A11 is the last event. Everything the engagement produced should be handed over in the agreed format at or before it — which requires the format question (open questions, item 1) to have been settled well before week six.