Skip to content

WS 1 — Immersion & Validation

Duration1 week
ObjectiveBuild a shared understanding of Manulife's existing technology landscape, target state vision, business objectives and work completed to date
FocusRapid immersion and validation of existing materials
DeliverablesD1.1 · D1.2

Tasks

IDActivity (SOW Schedule "A")OutputStatus
WS1-A1Project kick-off — align on objectives, scope, approach, roles and responsibilities, key stakeholders, engagement governanceKick-off record, stakeholder map, governance model
WS1-A2Review and assess existing client-provided materials — current state technology assessment, architecture artifacts, technology inventoriesClient resources — one page per artifact🟡
WS1-A3Assess the existing target state vision and architecture direction, including alignment to business objectives and technology strategyAssessment feeding D1.1🟡
WS1-A4Identify architectural questions, ambiguities, dependencies, risks and decisions to be addressed during the engagementOpen questions register🟡
WS1-A5Align on objectives, success criteria and the decision-making process for developing and socializing the target state and roadmapAgreed success criteria and decision forum

WS1-A2 — sub-tasks

IDArtifactStatus
WS1-A2aUnified customer architecture — strategy🟢
WS1-A2bThe Architecture Decision — options comparison🟢
WS1-A2cGARB ADS (MVP Phase)🟢
WS1-A2dSegment architecture assessment🟢
WS1-A2eMVP Canada EA analysis — readiness review🟢
WS1-A2fManulife Canada API landscape🟢
WS1-A2gUCX Canada experience map🟢
WS1-A2hConfirm the input set is complete — nothing else outstanding from the client → Client requests🟡

All seven have been read end to end and summarised with citations. WS1-A2 stays 🟡 until A2h closes — and A2h has already answered part of itself: reading the seven against SOW Schedule "A" produced 38 requests for material, access and people the set does not contain. The seven are not the whole picture.

Working notes

What the material actually establishes

There is a well-articulated target state (June 2026, Canada Segment EA), a well-articulated MVP that deliberately excludes most of it, and two client-authored critiques of that MVP — one recommending re-architecture, one returning a NO GO on the October date. Alongside them, two machine-derived inventories showing an estate in considerably better functional shape than the critiques alone would suggest.

The five cross-cutting observations are recorded on the client resources index. They are preliminary and need validating before they are shown to anyone.

The question this work stream really has to answer

"No agreed North Star" is concern #2 of the client's own executive readiness review, and finding F-02 of their own architecture assessment. It is stated, by them, in writing, twice.

That makes WS 1's validation activity narrower and sharper than it looks. We are not establishing what the vision is — there are candidate statements of it. We are establishing which one is of record, and who says so. Until that has a name attached, WS 2 is documenting a target state whose authority is unclear, and the client's own words say every decision built on it risks being reversed.

Things to raise at kick-off

  • Walk the client requests register — at minimum the 22 High items, which block named deliverables or sit on the critical path (WS1-A2h).
  • Confirm the calendar: the SOW's timeline is a graphic that did not survive conversion, so the schedule in Deliverables is derived, not quoted.
  • Establish who validates the vision, and in which forum.
  • Settle the handoff format, or at least agree when it will be settled — it gates both executive presentations. See open questions, items 1 and 3.
  • Establish access to the people behind each artifact. Several of our questions are answerable in ten minutes by their authors and not at all from the documents.

Ambiguities to resolve before WS 2

#AmbiguityWhy it matters
1Is the June 2026 strategy still Canada Segment EA's position?It is the only candidate North Star
2Is di-dashboard-services (Fastify, in DEV) the same thing as the ADS's Next.js Dashboard BFF?One is promote-to-PROD, the other is a build — different roadmaps
3Is the criticality dispute (Gold vs Critical Digital Properties) resolved?Every recovery number depends on it
4Is the ADS being revised, against which conditions, and on what date?Determines whether our target state lands into a moving or settled base
5Does our WS 2 output become the North Star of record?Changes what the deliverable has to be and who must approve it

Internal working knowledge base — not for external distribution.